03 HEALTH

GOVERNMENT HOSPITALS


Zola Hospital

Project Type Building Cost Gross Building Area Completion Date Client
300 Bed District Hospital R550 000 000 21 500m2 2013 Gauteng Department of Public Transport, Roads and Works

Lillian Ngoyi Hospital

Project Type Building Cost Gross Building Area Completion Date Client
300 Bed District Hospital with Ophthalmology Unit R480 000 000 21 700m2 Under planning Gauteng Department of Public Transport, Roads and Works

GOVERNMENT HEALTHCARE CENTRES


Zola Community Health Centre

Building Cost Gross Building Area Completion Date Client
R75 000 000 5 000m2 October 2010 Gauteng Department of Public Transport, Roads and Works

Eersterust Community Health Centre

Building Cost Gross Building Area Completion Date Client
R35 000 000 3 500m2 2009 Gauteng Department of Public Transport, Roads and Works

PRIVATE HOSPITALS


Centurion Hospital

Project Type Building Cost Gross Building Area Completion Date Client
176 Bed Private Hospital and Consulting Rooms R225 000 000 21 000m2 September 2014 Medi - Clinic

Kimberley Hospital

Project Type Building Cost Gross Building Area Completion Date Client
146 Bed Private Hospital and Consulting Rooms R185 000 000 1 500m2 July 2014 Medi - Clinic

Additions to Kloof Hospital

Project Type Building Cost Gross Building Area Completion Date Client
New Wards, Parking Area and Consulting Rooms R56 000 000 3 200m2 February 2013 Medi – Clinic

Cape Gate Hospital

Project Type Building Cost Gross Building Area Completion Date Client
150 Bed Private Hospital with Consulting Rooms R150 000 000 18 000m2 January 2010 Medi – Clinic

Medforum Hospital

Project Type Building Cost Completion Date Client
Upgrading of Various Areas R30 000 000 December 2010 Medi – Clinic

Meulmed Hospital

Project Type Building Cost Completion Date Client
Upgrading of Various Areas R102 000 000 August 2012 Medi – Clinic

Legae Medi - Clinic

Project Type Building Cost Completion Date Client
Upgrading of Various Areas R20 000 000 May 2012 Medi – Clinic

Potchefstroom Medi - Clinic

Project Type Building Cost Completion Date Client
Upgrading and Additions R4 000 000 November 2011 Medi – Clinic

Highveld Medi - Clinic

Project Type Building Cost Completion Date Client
Upgrading of Various Areas R7 900 000 November 2011 Medi – Clinic

Limpopo Medi - Clinic

Project Type Building Cost Completion Date Client
Upgrading and Additions R40 000 000 December 2013 Medi – Clinic

Cure Day Clinic

Project Type Building Cost Gross building area Completion Date Client
New Day Clinic and Consulting Rooms R25 000 000 3 100m2 November 2011 Cure Day Clinic Holdings

Pretoria Urology Hospital

Project Type Building Cost Completion Date Client
Upgrading of Various Areas R10 000 000 December 2009 Pretoria Urology Hospital

Pretoria Eye Institute East

Building Cost Gross building area Completion Date Client
R6 000 000 500m2 June 2008 Pretoria Eye Institute

Hart Hospital

Project Type Building Cost Completion Date Client
Upgrading of Various Areas R5 000 000 December 2008 Medi - Clinic
Paeds Upgrade R6 000 000 August 2013 Medi - Clinic

Wits Donald Gordon Hospital

Project Type Building Cost Completion Date Client
Upgrading of Various Areas R80 000 000 January 2013 Medi-Clinic

Ermelo Hospital

Project Type Building Cost Completion Date Client
Upgrading and Additions R6 000 000 September 2010 Medi -Clinic

Kloof Hospital

Project Type Building Cost Gross Building Area Completion Date Client
180 Bed Private Hospital R90 000 000 18 000m2 June 2005 Curamed Hospital Group

Lusaka Hospital

Project Type Building Cost Gross Building Area Completion Date Client
140 Bed Private Hospital R215 000 000 14 000m2 March 2011 Lusaka Premier Health